MTRJ_PIONEER-Challenges

2024.08.28_MTRJ002-PIONEER SHIPPING SCHEDULED TO SEPTEMBER 10TH
Assembly Challenges: As mentioned in the previous update, CNC manufacturing was initially scheduled to be completed by August 8th, with assembly expected to take two days. We anticipated that ever...
Read more
2024.07.15_MTRJ002-PIONEER Shipping Delay
Hi everyone, I wanted to share an update on our latest project and apologize for the shipping delay. We’ve been perfecting the design, going through five prototypes, each taking about 1-2 weeks. Ma...
Read more
Pioneer 002 Updates: 1.New transparent Edge Guide with engraved notes for each function: 2.New Transparent Rail guide attachment: 3. Previous plate to close router table opening is now chang...
Read more
MANUFACTURING CHALLENGES || Shipping Delay_00
This PDF was prepared to address the shipping delay in September, which resulted from assembly complications. Being my first product assembly experience, I overlooked the packaging aspect, which si...
Read more
MANUFACTURING CHALLENGES || Shipping Delay_00
This PDF was my initial attempt to explain the shipping delay, but I've since created an improved version to provide clearer information.
Read more
MANUFACTURING CHALLENGES || Shipping Delay_01
This was a PDF attached to an email that provided details about the shipping delay we experienced in October, along with an explanation for the delay.
Read more
Manufacturing Challenges || Factory Feedback_02
This PDF was sent to the CNC factory. It covers the fourth prototype they've made for us. There are only minor issues now, but the main concern is the incorrect engraving.
Read more
Manufacturing Challenges || Factory Feedback_01
This PDF is for the CNC manufacturing team. It's about our fourth prototype and the second one made by this factory after I made some changes.
Read more